Tavrida track start of construction. "Grandiose construction": how the Tavrida highway will change the life of Crimeans and tourists

After the return of Crimea to Russia, the development of the peninsula began with renewed vigor. The road that will connect Kerch - Simferopol - Sevastopol will allow guests of the republic to travel comfortably along the entire coast.

History of the Tavrida track

The construction of the Crimean Bridge changed the distribution of traffic flows on the peninsula. It became necessary to connect the opposite coast of the Crimea with the city of Kerch. This is how the project of the Tavrida road was born.
In 2016, the preliminary cost of the work carried out was calculated. The sum of 139 billion rubles was indicated.


In the same year, the route points were finally fixed, the main characteristics of the future road were developed. The track will be built in parts. Already existing roads will be used in some sections, a new route will be laid on others. The old roadbed, which is part of Tavrida, will be reconstructed to meet the requirements.

Route of the highway through the cities and interchanges

The road will pass through the following cities:

  1. Kerch
  2. Feodosia
  3. Belogorsk
  4. Simferopol
  5. Bakhchisarai
  6. Sevastopol

The length of the path is 250 kilometers. Thanks to modern infrastructure, the journey from Kerch to Simferopol will take no more than 2 hours. If you need to get to Sevastopol, the driver will spend no more than 3 hours on the road.
It is planned to create 6 launch sites. At the same time, work on the creation of interchanges is divided into stages:

  • At the first stage, the length of the track will be 70.8 km.... The route starts at the intersection of the Crimean bridge. The stage ends in the village of Primorsky.
  • Second phase... The road section will be 50 kilometers and it will end at the next junction. Here the road goes to Belogorsk-Lgovskoe and reaches the village of Lgovskoe.
  • In the third stage the path length is 35.6 km. From the village to the road leading to Simferopol and Feodosia. This is the area of ​​Belogorsk.
  • Stage 4... The length of the path is 27.5 km. From the road to Simferopol to the road leading to Bakhchisarai and Sevastopol.
  • Stage 5... 24.7 km. The track bypasses Simferopol and continues to move towards Sevastopol.
  • 6 stage... 28.9 km. The end of the path in Sevastopol.

In total, it is planned to create 17 transport interchanges along the route. At the same time, 90 bridges and overpasses will be built.

Road characteristics

How will the Tavrida track go on the Crimea map? When planning, calculations were made of the strength of the road surface, which was expressed in the load on the road. The indicator was taken from 21 to 39 thousand cars in 24 hours.


What are the characteristics of the new road connecting Kerch and Sevastopol:

  1. As a cover used asphalt concrete;
  2. The road under construction belongs to category IB;
  3. The permissible speed on the highway is 120 km / h;
  4. 4 lanes will be laid for the movement of cars. 2 lanes will lead in the direction of Sevastopol, the other 2 lanes in the direction of Kerch. In this case, the flows are planned to be split;
  5. On the Tavrida highway there is no provision for creating a single-level intersection with other roads.
  6. Will be erected bridges, overpasses;
  7. The designers made it so that the track does not pass through settlements, trying to bypass them as much as possible;
  8. For the convenience of pedestrians overhead passages will be built.

Tavrida road construction progress

The creation of the route began immediately after the approval of the plan and estimate. Construction is ongoing around the clock. Road workers do not have days off, so the road moves quickly. All work planned by the estimate is carried out on time, without delays or stoppages.


The project is divided into 7 stages. 6 stages of construction will take place on the territory of the Crimean peninsula. The last and final stage will take place in Sevastopol. The route is supposed to have 4 traffic lanes. The first two lanes are promised to open in December 2018. This will be the completion of stages 1 to 4. The remaining 4 lanes will be open by the 12th month of 2020.

The first stage of construction is underway. A section of the road, 70.8 km long, is being prepared: embankments are being made for the main course. The passing engineering communications are being altered. Small corrugated water pipes are being laid. The base of the road is being laid, consisting of geotextiles and gravel. Interchange bridges and tunnel overpasses are also being built.

As of January 2018, the asphalt has been paved over a section of 24 km. And a piece of two-way traffic is done.

Work is also underway at the second stage, where the section of the road leaves 50 m. 13.5 km of the road have already been asphalted here, as well as 2 lanes. Now earthworks are being carried out, engineering communications are being changed and altered, overpasses and interchange bridges are being built.

In the third section, they are working on a storm sewer system. The preparation of the roadbed, the installation of rainwater drainage, and the embankment of gravel are underway. 10 km out of 25.6 km are covered with asphalt.

Fifth stage. The general contractor creates infrastructure along the road. The track is also being improved by installing lighting lanterns. Both single-horn and 2-horn are installed.

In April 2018, the road workers reported that 88 kilometers were covered with asphalt without asphalt concrete. The readiness of the project is estimated at 29 percent.

As of the 7th month of 2018, 97.7 kilometers are covered with asphalt. At this, the first stage ends and the second stage of construction begins, where 39.4 kilometers of the highway, which are under asphalt, can be reported.

As of September 2018, builders say that the track is only 38% ready. If we look at the sections, then the section where the road comes to Simferopol. This road will open to traffic at the end of 2018.

When will the Tavrida highway be opened in Crimea?

The final launch of the track is planned for the end of 2020. But during the entire construction period, separate areas for the promotion of cars will decrease. The opening is divided into two stages:

  1. In the end current year (2018) must start two-lane car traffic... In total, there will be 4 lanes on the track;
  2. The second section leading from the mountain with the name "Sugar Loaf" to the road connecting Sevastopol and Yalta... No final decision has been made on this section of the route, since even the design documentation is not ready.

Where there will be no settlements, the road will increase to 4 lane traffic. The maximum permissible speed is 120 km / h. Inside the settlements, the Tavrida highway will merge into existing roads.

Construction cost

Preliminary calculations showed the need to provide 139 billion rubles. The budget of the Russian Federation allocated 14.36 billion for the continuation of the creation of the Tavrida highway.

Finds during the construction of the route

The Crimean Peninsula is a place where every centimeter of land contains various artifacts. What names were found during the construction of the bridge:

  • At the very beginning of the project, things belonging to the Bosporan kingdom... This happened on the Tiriktan shaft. There is a debate about what kind of massive structure it is.
    Shaft attachment systems were found along with other finds. Artifacts date back to the 4th - 3rd century BC;
  • Was first warehouse found;
  • In the southeastern part of the city Kerch mound discovered.

Gradually, they moved from ancient artifacts to the events of our time. For example, the stone bridge built by Catherine II. This is both the bridge and the excavation of a part of the road.
A karst cave was discovered in the Belogorsk region.

The new ring road around Simferopol is a long-standing project, which began with the work of KrymNIIproekt at the turn of the 1970s and 1980s.

Simferopol ring road.
The yellow line is the site under construction, the gray line is the design.

From the airport (now old, new terminal will be launched by the season 2018) the Okruzhnaya section on Dubki was built in Ukraine. The highway from the Fontana microdistrict was brought to the village of Klinovka and Tyoploy Balka, where the Crimean deputies established their villas. By the time it was taken to the trolleybus line near the village of Pionerskoye, there was nothing left to finish.

  • , phone +79787617496 Evgeniy. Call, meet, talk to the driver on the way to the resort and plan trips to the most interesting places Crimea for the whole vacation.

Okay, about the good: we will tolerate a little the inconvenience of temporary detours of the 2018 season, but by August 30, 2018, the first high-speed, in the standards of the Tavrida federal highway, the SKAD section of the Simferopol ring road will be open to traffic.

Official data:

The four-lane Dubki - Levadki bypass road of category 1B will stretch for 9.1 kilometers. The area of ​​the roadbed will be 170 thousand square meters, with a carriageway width of 15 meters. It is necessary to relocate the main gas pipeline, a water pipeline, several power transmission and communication lines, build three overpasses, a crossing over railway tracks and a transport interchange on the highway to Sevastopol. In addition, six culverts with a length of 343 meters will be laid. To protect the subgrade from waterlogging and erosion, surface drainage systems are provided. Fences and lighting will be installed on the road. The warranty period is eight years. The estimated speed of movement along the section of the route will be 120 kilometers per hour. The construction cost of the facility is 6.15 billion rubles, the completion of the work is planned for August 30, 2018.

Video.
How the Tavrida highway is being built near Simferopol on the Dubki-Levadki section. In the video, we fly in two places. Half a video in the Dubkov area, and the other half in the Levadkov area ...


The northeastern sector of the SKAD: a new terminal at Simferopol airport and a new bus station Central. State farm. Bituminous. Yielding. Picturesque. Tavrida track near Trudovoe village.

The federal highway Tavrida from the east of Feodosia and Kerch goes to the Simferopol airport and the new Central bus station from the Trudovoye village, namely through the dacha massif Ilyushino, Beloe, Aikovan, Solnechnoye, Bitumnoye and Sovkhoznoye.

The owners of summer cottages may not worry, the map shows that the Tavrida highway does not affect the summer cottages. But the conditions will dramatically improve, as well as the cost of the plots.
For example, in the suburban area Trudovoye there will be a gas station, and a very large transport interchange, which will allow you to get to the airport in 5 minutes by car, and Dubkam in 10-15 minutes, and leave for Sevastopol or Nikolaevka.

Section of the federal highway Tavrida near the new terminal of Simferopol airport and Central bus station

The approximate average speed on the circular highways around Simferopol will be 120 km / h. Well, the customers plan to complete the construction by 2020, and this is already a year of commissioning the highway, but according to forecasts, it should be completed even earlier, simultaneously with Crimean bridge... The construction of a transport crossing through the Kerch Strait is going ahead of the plan.

The southern half of the SKAD will connect through Livadki and Pionerskoye - Sevastopolskoye and Yalta highways. And through Trudovoye, the new Simferopol TPP, Denisovka, Pionerskoye - Feodosiyskoye and Yalta highways.

The first block of the Simferopol TPP thermal power plant will be commissioned in 2018. The SCAD bypasses the TPP on top. In the photo on the left there is a direction to Trudovoe, on the right to Denisovka. At the bottom of the highway Stroganovka - Denisovka - Ivanovna. View from the Ostrich Farm

A bridge will be built across the Maly Salgir River on the southeastern outskirts of the village of Denisovka. Four lanes of high-speed car traffic is something amazing for the local scale. However, it is quite consistent with the size of the new power plant. In short, there will be a city here. By the way, in order to unload Simferopol, the authorities and designers are considering options for the construction of several satellite cities and suburban elite settlements, as well as residential neighborhoods.

The exact data on the alienation of land plots for the federal highway Tavrida and SKAD are posted in village and settlement councils. Property owners receive compensation.

Construction of the federal highway "Tavrida"

Crimean federal high-speed highway "Tavrida" will be completed by 2020. The first part of the road, Kerch-Simferopol, will be put into operation together with the opening of the Krechinsky bridge in 2018, the rest and the final part will be completed by 2020. It is assumed that it will be one of the most beautiful high-speed highways in the south of Russia!

The work has already begun and a lot has been done, we will talk about this further, on March 30, 2017, all design and estimate documentation was ready, plus a feasibility study and financial audit were also completed.

What will be the new Tavrida track:

The length of the route will be 280 kilometers, the road will run from Kerch to Sevastopol. The track of the first category, equipped with four lanes and high-quality road surface, made in accordance with all modern standards. Poles with lighting and concrete dividers will be installed along the entire route.

According to all plans, within 40 years "Tavrida" will need neither repairs, nor expansion, nor reconstruction. The road speed will be 120 km / h. What Crimea really lacks!

Where the Tavrida track will pass.

The route starts from Kerch towards such villages as Lugovoye and Batalnoye, where the old route has already been reconstructed and a new section of the road to the village of Vladislavovka is approaching the end. In the Belogorsk and Kirovsky districts, the highway has been laid at a new location, where it will enter the current Belogorsk-Simferopol highway, it is already being reconstructed and expanded in accordance with the requirements of the first category highway. From Belogorsk, the highway will pass towards Pionersky, south of Simferopol, after which it will connect to the highway to South coast Crimea and the city of Yalta. Further, the road will go to the village Pleasant Date. The highway will also bypass Bakhchisarai. In more detail, in the schemes for the passage of the Tavrida route, you can find out from the current on this moment information.

What is the Tavrida track for?

The route will be located bypassing all settlements, as well as protected areas of the peninsula, forming a single transport system... It is planned that the reconstruction of the Don highway - namely, bringing it to the 1st category (the permitted speed of cars is 120 km / h), as well as access to Kerch bridge, which will connect the resorts of Crimea with the high-speed corridor of Moscow and St. Petersburg and other passing cities of Russia. The cost of the Tavrida project should not exceed 140 billion rubles. Residents of Crimea are eagerly awaiting the start of a historical infrastructure project, which, in terms of its size, will forever change the peninsula.

"Crimea, Tavrida highway, latest news" - this can be seen in numerous headlines mass media and on the Internet. This speaks of the importance of the upcoming event. The Crimean administration, which is in charge of the construction, expects that it will be completed by 2019. The Tavrida route scheme was submitted for approval along with the estimate documentation at the end of 2015. This major project began in early 2016.

Here you can find out another useful information about.

Federal highway Tavrida: benefits for Crimea

It is planned to simultaneously commission two important objects. The Tavrida highway and the bridge across the Kerch Strait will help attract even more tourists to the resorts of the peninsula. The status of an important road is declared as federal and high-speed. Its length will be 260 kilometers. Resolved, where will the Tavrida track in Crimea. It will connect two major centers of the peninsula: Kerch and Sevastopol, bypassing Simferopol. Thus, the freeway will become an important facility that will operate in a busy mode. She is expected to have elevated level strength.

Tavrida highway (Crimea) will have 4 lanes... For 40 years, it will not require repairs, due to the high strength of the materials used for construction. All structures along the road will also be rebuilt. Presumably Tavrida road will cost 45 billion rubles... It is planned to commission a highway and a bridge in 2019, which will have to connect the mainland and the peninsula. This large-scale construction will help improve the traffic situation in Crimea.

Tavrida track: latest news and highlights

The Tavrida track, news about which interests both the inhabitants of the peninsula and those who plan to go to the resorts, will have the 1st level. This will allow to develop transport speed up to 140 kilometers per hour... Tavrida highway, Crimea, the beginning of construction will accelerate movement within the peninsula.

The developers promise that the Tavrida road, the scheme of which has already been presented to the public, will meet international standards. The motorway will not affect large settlements and beautiful nature reserves.

The construction of the Tavrida highway will be like this. It is planned to do branches to villages along the road... In the area of ​​the cities of Feodosia and Sudak Tavrida, the Crimea road will have access to the sea, for the convenience of those who come to rest. Tourists traveling around the peninsula will be able to freely access any resort or cultural center for sightseeing.

How the Tavrida Crimea track will go, the 2019 scheme of which is presented in this article, is no secret to anyone. The inhabitants of the peninsula are eagerly awaiting the appearance of the road. It will be convenient for travelers and locals.

Tavrida Crimea route scheme on the map

To find out federal highway Tavrida, where it passes on the map, it is necessary to refer to the scheme of the peninsula. It is supposed to lay it on the following sites:

  • Reconstruction is planned from the city of Kerch to the village of Lugovoye;
  • According to the plan, a new Tavrida road will be laid to Vladislavovka on the map of Crimea;
  • In the Kirovsky and Belogorsky districts, the Tavrida highway, Crimea, the 2019 scheme of which is clearly visible, will lay in a new place for construction;
  • Improvement of the road will be carried out on the section between Belogorsk and Simferopol;
  • Further, the project of the Tavrida route on the map will continue in the direction of Pionersky;
  • Then she will walk past Simferopol through the settlement Pleasant Date;
  • The Tavrida highway on the Crimea map will have an approach to the Tsentralny airport;
  • Without affecting settlements, the highway will approach the trolleybus line between Alushta and Yalta.

The Tavrida highway project fully meets the requirements of the modern peninsula. This road will provide an opportunity to discover new places for tourism. Currently, the area of ​​the Maly Salgir River is not fully developed. Tavrida track, Crimea, a detailed diagram shows that it will be possible to open these places for vacationers. The Tavrida track plan clearly demonstrates its necessity and importance.

In May of this year, an official event took place, within the framework of which a stone was laid, which became a symbol of the beginning of construction work. on the Tavrida highway... Crimean authorities claim that the construction of the new highway will be completed by December 2020. All accompanying documentation for the Tavrida highway was submitted for approval back in 2015.

Benefits of the route for Crimea

The simultaneous completion of the construction of two large-scale projects is expected: the Tavrida highway and the bridge over the Kerch Strait. This will help attract a huge number of tourists to the resorts on the peninsula. The length of the entire road will be about 260 kilometers. The new Tavrida highway will be a link between Sevastopol and Kerch.

Features of the Tavrida track

Cars will be allowed to drive at speeds up to 130 km / h, because the track is high-speed. On the Crimean section, about 20 gas stations and 6 special road service zones will be erected and put into operation. There are plans to build motels, food outlets and even dedicated charging points for electric vehicles. The work will involve about three and a half thousand highly qualified workers.

All construction work on the reconstruction of old roads will begin in June this year.

According to the project, two of the four lanes of the route will be put into operation by December 2018. This route will have four lanes and it is assumed that during 50 years no repairs are required due to the use of the latest technologies and the most durable materials during the construction process. The highway will become as convenient as possible for both new travelers and the indigenous population.


Scheme and stages of construction of the route

Now we will try to figure out how the Tavrida Crimea circuit will pass. The diagram shows that Kerch will be connected with the cities of Simferopol and Sevastopol using the erected bridge. 19 km bridge will be the longest in Russia. It will connect the Crimean peninsula with the road and railways of the Russian Federation. Transport will be open in December 2018, and trains a year later.
It is planned to build:
23 overpasses;
15 bridges;
31 passages for agricultural machinery;
35 overhead pedestrian crossings;
4 lanes;

It is known that the construction will take place in 6 stages. As you can see in the diagram, the construction process will begin in the village of Primorskiy, then in the Lgovskiy district. In the third stage construction will take place in the city of Belogorsk... At the next stage, the roads between Simferopol, Bakhchisarai and Sevastopol will be connected. Construction work will end in the area of ​​the village of Levadki.


Construction of a highway near Simferopol

Tavrida Crimea route scheme near Simferopol has its own characteristics. The route will pass through 8 villages of the Simferopol region. The new road will improve the transport connection of western settlements with Simferopol and allow for the movement of freight transport. Also, the new track will attract tourists.